| Electricity Connection | ||
| Reform ID | S677 | |
| Description | K-Electric's new industrial connection process takes about 80 days despite partial digitization, requiring extensive documentation already available with NADRA, FBR, and SECP, alongside multiple manual internal approval stages, deficiency-driven resubmissions, and repeated physical visits. | |
| Department | K-Electric | |
| Jurisdiction / Location | Sindh | |
| Sector | Fisheries | |
| Start Date | 23-07-2026 | |
| Target Deadline | ||
| Date Enacted | ||
| Implementation Status | In Progress | |
| Progress | 0% | |
| CCORR Direction | ||
| Cost Savings PKR (Mil.) | 1,481.00 | |
| Evidence | ||