| Specify timeframe for processing of NoCs/permits for low risk buildings and to permit applicant to start construction if objection/ rejection is not conveyed with in the timeline. | ||
| Reform ID | S141 | |
| Reform Description | Before: There was no timeframe specified for approval of building plans which caused delays in building plans approvals
After: Now, with specific timelines for issuance of NoCs/Permits in place the process has become efficient. |
|
| Sector | Construction | |
| BeneficiariesAutomotive Owners | All businesses | |
| Jurisdiction/ Location | Sindh | |
| Department | Sindh Building Control Authority (SBCA) | |
| Date of Implementation | 27-01-2020 | |
| Details | Difficulty | Without any timelines for issuance of NoCs/Permits required for low-risk buildings, the process was inefficient which added more cost and delayed the construction process. |
| Analysis | It was felt that there is a dire need to specify timelines for the issuance of NoCs/Permits to speed up the construction process. | |
| Solution | After the detailed deliberation it was agreed that there should be a specific time limit within which the NoCs/Permits are issued. Accordingly, the competent authority notified the revised regulations | |
| Evidence | Evidence | |