Specify Timeframe for Processing of NOCs/Permits for Low-Risk Buildings and to Permit Applicant to Start Construction if Objection/ Rejection is not Conveyed within the Timeline
Reform IDA173
Reform Description
Specify Timeframe for Processing of NOCs/Permits for Low-Risk Buildings and to Permit Applicant to Start Construction if Objection/ Rejection is not Conveyed within the Timeline

Before: There was no timeframe specified for approval of building plans which caused delays in building plans approvals.

After: With specific timelines now established for the issuance of NOCs/Permits, the process has become more efficient.

SectorManufacturing - Construction
BeneficiariesAll Businesses
Jurisdiction/ LocationAzad Jammu and Kashmir
DepartmentAJK Development Authority
Date of Implementation
DetailsDifficultyWithout any timelines for issuance of NOCs/Permits required for low-risk buildings, the process was inefficient which led to increased costs and delays in the construction process.
AnalysisIt was felt that there is a dire need to specify timelines for the issuance of NOCs/Permits to speed up the construction process.
SolutionAfter the detailed deliberation, it was agreed that there should be a specific time limit within which the NOCs/Permits are issued. Accordingly, the competent authority notified the revised regulations.
Evidence