| Setting a clear timeframe for NOC/permit processing for low-risk buildings, allowing construction to begin if no objection is raised within the timeline | ||
| Reform ID | P195 | |
| Reform Description | Setting a clear timeframe for NOC/permit processing for low-risk buildings, allowing construction to begin if no objection is raised within the timeline Before: There was no specified timeframe for the approval of building plans, leading to delays in the process. After: Now, with specific timelines for issuance of NOCs/Permits in place, the process has become efficient. | |
| Sector | Manufacturing - Construction | |
| Beneficiaries | All Businesses | |
| Jurisdiction/ Location | Punjab | |
| Department | Lahore Development Authority - LDA | |
| Date of Implementation | 28-01-2020 | |
| Details | Difficulty | Without any timelines for issuance of NOCs/Permits required for low-risk buildings, the process was inefficient which added additional cost, and delayed the construction process. |
| Analysis | It was felt that there is a dire need to specify timelines for the issuance of NOCs/Permits to speed up the construction process. | |
| Solution | After detailed deliberation, it is agreed that the building plan for a residential plot would be approved within 21 days, for commercial plots within 30 days, and for all other buildings within 45 days. | |
| Evidence | View Evidence | |